Pollution Prevention and Control Technologies for Plating
Operations
Section 4 - Chemical Solution Maintenance
4.4 ION EXCHANGE
4.4.5 Costs
4.4.5.1 Capital Costs
4.4.5.2 Operating Costs
4.4.5.1 Capital Costs
A diagram showing the equipment costs for the application of ion
exchange to chromic acid baths is presented in Exhibit 4-10. Installed
costs for these systems are approximately 10 to 30 percent higher
than basic equipment costs.
4.4.5.2 Operating Costs
Operating cost data provided by respondents to the Users Survey
are presented in Exhibit 4-11. The annual costs and savings for
the respondents are shown graphically in Exhibit 4-12, which also
expresses capital costs in terms of 1993 dollars. This graphic
indicates that a relatively rapid capital payback is possible
with this technology (see bar graph for PS 049 and PS 191).